HAZOP Study for AU,VDU,VBU,BBU,DCU,VGO-HDT, ATF MEROX,COKER MEROX, FCC LPG,MTBE,FPU,CRU,ISOM,SRU,ARU,HGU,DHDT,SWS,CGP,DHDS,TPS FGH Process Units of IOCL Gujarat Refinery

INTRODUCTION

Gujarat Refinery, IOCL’s 3rd largest Refinery,  is located at Koyali, Vadodara District in Gujarat, Western India. It is currently under production expansion, projected upto 18 million tonnes per year. M/s. Indian Oil Corporation Ltd. (IOCL) had floated a tender to conduct the Hazard and Operability Study (HAZOP) for the Gujarat Refinery in line with OISD guidelines which has been awarded to IFLUIDS Engineering.

HAZOP Study Objective

The HAZOP study objective is to identify hazard and operability problems, to reduce the likelihood and severity of an incident in the process units, utilities & offsite facilities in the Indian Oil Corporation Ltd. (IOCL) that pose a serious impact to the plant, personnel, properties and environment.

Methodology of HAZOP

  1. Node mark-up based on (Stream, Equipment or  Package) on the P&ID
  2. List all the intention & process parameters for that node
  3. List all deviations and disregard deviations that are not meaningful within the Node
  4. Brainstorm and list the various causes of deviation and disregard causes that are not credible
  5. Brainstorm the consequences of the deviation for all the listed credible causes
  6. Identify Safeguards already provided in the system
  7. Apply Risk Matrix based on severity & likelihood
  8. Propose recommendations wherein the safeguards are found inadequate

Scope of work:

HAZOP Study of Gujarat Refinery has been carried out in two phases, such as :

  • Phase 1- 41 Process Units
  • Phase 2 – Offsite / tank farm

Phase 1 of HAZOP study:

The total number of P&ID’s for 41 process units assessed was approximately 1333 Nos.

Phase 2 of HAZOP Study:

The total number of P&ID’s for offsite / Tank farm assessed was approximately 150 Nos.

Process Units at Gujarat Refinery:

S. No.Process Unit   No. of P&ID
1AU-0413
2VDU11
3VBU13
4BBU9
5DCU182
6VGO-HDT117
7ATF MEROX32
8COKER LPG MEROX33
9FCC LPG MEROX24
10MTBE22
11AU322
12HCU76
13FPU-231
14HGU-115
15FCCU54
16FPU-113
17Nitrogen unit18
18AU-129
19AU-221
20AU-527
21CRU29
22ISOM97
23SRU-367
24ARU-336
25SWS-116
26SWS-216
27HGU-346
28DHDT41
29DHDS64
30HGU-229
31008SWS-15
32008SWS-25
33898SWS-45
341012SWS-55
35SWS-65
36ARU-67
37SRU-29
38CGP-118
39CGP-229
40TPS34
41CETP8

Project Duration: 15 Months