Evaluation of Specified Insurance Risk Observations / Recommendations For QP Refinery Operational Area

Qatar Petroleum (QP) is a state-owned public corporation established in 1974. Qatar Petroleum is in charge of all aspects of the oil and gas industry in Qatar. The main activities of QP, its subsidiaries, and joint ventures are the exploration, production, local and international sale of crude oil, natural gas and gas liquids, refined products, synthetic fuels, petrochemicals, fuel additives, fertilizers, liquefied natural gas (LNG), steel, and aluminium. QP owns and operates a Refinery at Mesaieed, located about 35 Km. South of Doha City in the State of Qatar.

The project was awarded to iFluids Engineering on a consultancy basis to study, research, and evaluate specific insurance risk observations / recommendations made by QP Insurance Assessors relating to QP Refinery.

Scope of Work

  • Study reports & recommendations from Phase-1, Consultancy for Refinery Insurance Survey Recommendations at QP refinery, Mesaieed
  • Study observations  and recommendations related to Passive Fire Proofing, Fire escalation, Pool Fires, and Jet Fires
  • Assessment of consequence analysis related to Fire Escalation / Pool Fires including:

a) Pool fire leading to running liquid fire

In fire zones susceptible to pool fire, the fires should be controlled  from  spreading across the floor into adjacent zones and equipment. It is recommended that kerbing and drainage is installed in each discrete fire zone to capture and limit liquid fire spread and to assist the fire team in controlling the fire by the application of a foam blanket seal.

b) Pool and jet fires in compressor house

It is recommended that the consequence analysis is used to review the duration and intensity of pool fire and jet fires with respect to the Steelwork supporting compressor house such that the structure does not fail in a fire scenario. It is recommended that passive fire protection be applied to all compressor houses structural supports deemed vulnerable by such analysis.

Standards & Codes used

NFPACodes and standards
OSHA 29 CFRRegulation pertaining to work in confined areas
API 2217Guidelines for work in inert confined spaces in the petroleum industry
BS 5973Code of practice for access and working scaffolds and special scaffold structures in steel.
QP-PHL-S-001QP Corporate fire and safety philosophy
QPHSE Safety regulations for CONTRACTOR
QPOnshore and offshore safety standards
QP-SPC-V-001EMS Specification for waste management.
QP-GDL-V-001-5EMS Guidelines: waste (solid and liquid) management
NIOSH (U.S.A).Occupational safety and health guidelines for chemical hazard
HSE (U.K.).Control of substances hazardous to health regulation, 1999
QP-REG-S-001QP HSE Regulation for CONTRACTOR
HSEPR-QP-11Procedure for managing HSE in Contract
HSEGL-QP-11-10Guide line for managing HSE in Contract
SHELL DEPSHELL Design Engineering Standards

Deliverable

  • Submission of Inception Report (Site survey)
  • Submission of Detailed Recommendations on QRA, Consequences analysis, DBM   &   Designs   for   the   Construction
  • Submission of final consolidated report including recommendations, designs, Specifications, updated Consequence Analysis

Completion Period

The Completion period of the project was over 12 months.